How Can Unfinished Construction Be Completed by Another Contractor?

Real Estate
Before arranging completion of unfinished construction by another contractor, establish whether the existing agreement remains in force and which works remain outstanding. Agreed continuation, completion at the original contractor’s expense where the legal requirements are met, and ending the agreement before engaging a replacement involve different documents and steps. A new quotation does not by itself resolve the original contractor’s obligations or the status of title shares already transferred.
Identify the Remaining Work and the Existing Relationship
Read the agreement with all annexes, extensions, notices and earlier payments. Record when work stopped, why it stopped, the landowner’s performance and the contractor’s explanation. If the objective is to complete the building promised under the current agreement, assess how a notice purporting to end that agreement would affect the intended claim before sending it.
A technical assessment should distinguish completed work, incomplete and defective work, usable materials and the cost of the remaining work. If a replacement proposes removing or rebuilding earlier work, establish the reason. Consider preservation of evidence before the site changes. The technical cost estimate and the original contractor’s legal responsibility require connected but separate assessment.
Agreed Continuation and Transfer of the Agreement
If the original contractor, replacement and landowners can agree, written terms can identify each person’s work, account for previous payments and address delay claims and security. Engaging someone to perform particular works has different effects from transferring the entire agreement. A transfer under Article 205 of the Turkish Code of Obligations requires the participation or necessary permission/approval of the party remaining in the agreement and compliance with the form required for the transferred agreement.
The protocol should address possession of the site, ownership of materials, responsibility for earlier work and acceptance of new work. Required steps concerning the permit, contractor records and building supervision should also be established with the competent technical professionals and authority.
What Supports Completion at the Original Contractor’s Expense?
Article 113 allows a creditor to seek permission for an unperformed obligation to do something to be performed by the creditor or another person at the debtor’s expense. For this remedy, commonly called nama ifa, the requested permission, remaining work and expense calculation must be defined. A budget should not assume that every replacement contractor’s charge will automatically be recoverable from the original contractor.
Article 473(2) provides a specific rule where, during construction, it becomes clear that the work will be defective or contrary to the agreement through the contractor’s fault. Notice requires correction within an appropriate period and warns that otherwise repair or continuation will be entrusted to a third party at the contractor’s risk and expense. Establishing these conditions requires a different assessment from simply showing delay or an empty site. The notice, period allowed and need for judicial permission must be assessed under the legal basis selected.
Documents to Prepare Before Accepting a Replacement Offer
- The original agreement, specifications, project, permit and all supplementary protocols.
- Chronological notices, work programme, payments and progress-payment records.
- A technical schedule of progress, outstanding work, defects and materials, with a cost estimate.
- Current title and encumbrance records, previous share transfers, third-party agreements and security.
- Comparable itemised quotations, the funding source and proposed payment schedule.
If completion is to be funded by selling units said to belong to the original contractor, ownership, authority to sell and any judicial authorisation required need separate examination. Seeking completion does not itself authorise a unit sale or taking possession of the site by unilateral action. The new agreement should address existing rights, permissions and the outstanding account.